Friday, August 25, 2017

Asphalt Surface Paving Being Scheduled

Work Performed, August 21st to August 25th
·         Internal televising of storm and sanitary sewer pipes.

Work to be Performed
·         Pave final layer of asphalt
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

The Village is continuing to work with the contractor to schedule the final surface layer of asphalt as soon as possible.

Friday, August 18, 2017

Final Surface Layer of Asphalt Pavement being Scheduled

Work Performed, August 14th to 18th  
·         Graded and installed topsoil
·         Adjusted structures to final grade
·         General site clean-up.
·         Miscellaneous tasks prior to project close-out.

Work Anticipated to be Performed, August 21st to August 25th  
·         Pave final layer of asphalt
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

Asphalt paving was not performed as anticipated due rain and threat of rain on Thursday and Friday. We are anticipating the final asphalt layer will be paved next week. We will provide a notice of the paving schedule.

Monday, August 14, 2017

Preparing for Paving Final Layer of Asphalt Pavement

Work Performed, July 31st to August 11th  
·         Graded roadway prior to paving first layers of asphalt
·         Paved first layer of asphalt pavement
·         Rough graded landscape areas behind curb & gutter.
·         Replaced asphalt driveways as needed.
·         Perform testing of water main system as required per Village requirements

Work Anticipated to be Performed, August 14th to August 18th  
·         Make final adjustments to structures prior to paving
·         Install and grade topsoil
·         Pave final layer of asphalt.

The contractor has continued to grade and install topsoil in the areas of landscape restoration; however, the sod will not be installed until mid-September when growing conditions are more favorable.

With the first layers of asphalt installed, the amount of dust was greatly reduced and a smooth driving surface was provided.

We are hopeful the majority of the construction work will be completed in the next 1-2 weeks with the exception of sod installation.

Thank you again for all your patience and understanding as you deal with construction along Linneman Street and Harlem Avenue throughout the construction season.