Friday, September 1, 2017

Asphalt Surface Paving Being Scheduled

Work Performed, August 28th to September 1st  
·         No work completed on-site.

Work to be Performed
·         Pave final layer of asphalt
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

The Village is continuing to work with the contractor to schedule the final surface layer of asphalt as soon as possible.