Work Performed, June 26th to June 30th
·
Received necessary approvals to place new water
main into service.
·
Replaced all water services to residences and
United Methodist Church / School
·
Made final connections to existing water main.
·
Completed storm sewer along roadway
·
Replaced storm sewer services to those homes
with previous connections.
Work Anticipated to be Performed, July 3rd to
July 7th
·
Contractor is expected to work on-site on
Monday, July 3rd
·
No
work anticipated on-site on Tuesday, July 4th
·
Complete
remaining underground utility improvements, only minor items remain
·
Begin
roadway reconstruction
Roadway
reconstruction will begin next week. This phase of construction will consists
of removing the existing concrete pavement, repairing any areas of the existing
soil below the pavement that are failing, installing new aggregate base, new
concrete curb & gutter, and asphalt pavement.
During roadway
construction, access to Linneman Street will be limited during working hours.
As you have been dealing with over the past several weeks, heavy construction equipment
and work has made it very difficult to travel along Linneman Street. During
working hours, the contractor will be excavating the entire roadway width to
remove the existing pavement and perform the work associated with
reconstructing the roadway. We ask that you remove your vehicles prior to
working hours, then following work completing for the day, you will have access
to your driveways. During concrete curb
& gutter installation, driveway access will be restricted for approximately
5 days. The Village of Glenview will be hand-delivering letters with exact
dates of the driveway and travel restrictions as well as parking options,
please be on the look-out for these letters on your front door.
As
stated in previous posts, since this project is funded by the Village of
Glenview, construction will not be delayed due to the current shut-down of IDOT
projects.
Have a
safe and enjoyable July 4th Weekend.