Poured concrete curb & gutter
·
Poured concrete driveways
·
Prepared for paving first layer of asphalt
pavement.
Work Anticipated to be Performed, July 31st to
August 4th
·
Pave first layers of asphalt pavement
·
Complete driveway restorations
·
Rough grading of landscape behind curb &
gutter
Thank you for all your understanding as driveway access has been restricted during concrete curb & gutter construction. Driveway access will be restored once the concrete is properly cured and the first layers of asphalt pavement are installed.