Saturday, July 29, 2017

Concrete Work Completed. Paving Next Week.

Work Performed, July 24th to July 28th
·         Poured concrete curb & gutter
·         Poured concrete driveways
·         Prepared for paving first layer of asphalt pavement.

Work Anticipated to be Performed, July 31st to August 4th 
·         Pave first layers of asphalt pavement
·         Complete driveway restorations
·         Rough grading of landscape behind curb & gutter

Thank you for all your understanding as driveway access has been restricted during concrete curb & gutter construction. Driveway access will be restored once the concrete is properly cured and the first layers of asphalt pavement are installed.