Graded roadway prior to paving first layers of
asphalt
·
Paved first layer of asphalt pavement
·
Rough graded landscape areas behind curb &
gutter.
·
Replaced asphalt driveways as needed.
·
Perform testing of water main system as required
per Village requirements
Work Anticipated to be Performed, August 14th
to August 18th
·
Make final adjustments to structures prior to
paving
·
Install and grade topsoil
·
Pave final layer of asphalt.
The contractor has continued to grade and install topsoil in
the areas of landscape restoration; however, the sod will not be installed
until mid-September when growing conditions are more favorable.
With the first layers of asphalt installed, the amount of
dust was greatly reduced and a smooth driving surface was provided.
We are hopeful the majority of the construction work will be
completed in the next 1-2 weeks with the exception of sod installation.
Thank you again for all your patience and understanding as
you deal with construction along Linneman Street and Harlem Avenue throughout
the construction season.