Friday, August 25, 2017

Asphalt Surface Paving Being Scheduled

Work Performed, August 21st to August 25th
·         Internal televising of storm and sanitary sewer pipes.

Work to be Performed
·         Pave final layer of asphalt
·         Sod Restoration, to be performed in mid-September when growing conditions are typically more favorable.

The Village is continuing to work with the contractor to schedule the final surface layer of asphalt as soon as possible.