Friday, June 2, 2017

Construction Starts June 5th

Welcome to the Linneman Street Improvements Blog!!!

This blog will typically be updated once per week, usually on Friday, detailing the work completed the previous weeks and work anticipated to be completed the upcoming week. It will also include information regarding the construction operations.  We hope you find the posts useful and informative.  The Village of Glenview will also be delivering letters to your front doors on occasion detailing specific information regarding water shut-downs and driveway restrictions. Please be on the lookout for these letters.

Week Completed, May 30th to June 2nd  
·         Construction lay-out for work to be performed
·         Saw-cutting

Work Anticipated to be performed next week, June 5th to June 9th
·         Sanitary sewer service replacements

The Village will do everything possible to minimize the inconveniences during construction, but unfortunately some are unavoidable.