Work Performed, June 12th to June 16th  
·         Completed water main installation
·         Complete sanitary sewer service replacements
·         Continued to remove existing sanitary sewer in middle of roadway

Work Anticipated to be Performed, June 19th to June 23rd
·         Perform necessary testing and receive necessary approvals to place new water main into service
·         Begin storm sewer installation