Completed water main installation
·
Complete sanitary sewer service replacements
·
Continued to remove existing sanitary sewer in
middle of roadway
Work Anticipated to be Performed, June 19th to
June 23rd
·
Perform necessary testing and receive necessary
approvals to place new water main into service
·
Begin storm sewer installation
We appreciate your patience and understanding during the
construction.